That is the direction of the Deputy Minister of Construction Cao Lai Quang on Conference 2010 business review and discuss measures Vienam Industrial Construction Group in 2011. With the effort of the Group for the progress accomplished on key projects, particularly the completion of construction of Son La hydroelectric power plant over a two-year schedule.
|
24th January, the building Son La hydropower plant, General Confederation of Labour of Vietnam has successfully held a conference to summarize 5 years (2006-2010) "Emulation movement link building Son La hydro power plant" and emulate the period 2011-2012.
|
In 2010, the Song Da Corporation have almost completed their objectives, progress and ensure quality construction of key projects: Son La Hydropower, Ban Ve, Ban Chat, Vung Ang 1 thermal power plant, Nhon Trach 2. .. Ensure goals of preventing flood in 2010 and works to prevent river hydropower: Hua Na, Xekaman 1. In particular, completion of construction and power generation: 2 units, Ban Ve hydropower, Pleikrong , Se San 4, Son La and gas turbines of a Thermal Power Plant 2 ...with construction value reached 102% of the plan.
|
In the evening of January 16th, at the Son La hydropower plant, the rotor weighs 1,000 tons have been absoluted safety installed to the correct position of the combined unit 2 by workers of Lilama 10 JSC.
|
At this time would be too early to answer: Is Lai Chau hydropower capacity of barely half of Son La hydropower has created the miracle, a new record, how glorious or not? Just know that by starting on time, benefiting over 3,000 billion, Lai Chau hydropower seems prolonged period of performance of Son La hydropower.
|
On January 5th, at Nam Hang commune, Muong Te district, Lai Chau province, Vietnam Electricity Group (EVN), Lai Chau province and Construction Industry Corporation of Vietnam (VNIC GROUP) has formally started Lai Chau hydropower projects. Attending the ceremony were Prime Minister Nguyen Tan Dung, deputy head Hoang Trung Hai, Chairman of National Assembly National Council Ksor Phuoc, Minister of Industry and Trade Vu Huy Hoang and Minister of Construction Nguyen Hong Quan ...
|
On 25th of December, in Muong La, Son La province, the State Inspection Council has inspected works and projects at the request to generate unit No. 1 Son La hydropower plant.
|
Top of the stairs is the main line of Song Da River, Lai Chau hydropower plant are expected to begin in late May 12-2010. Investor and the contractor has started to work for several months, construction space is being expanded, many large items are conducted expeditiously. Beginning in the dry months, as more vibrant at Construction site, working three shifts continuously, not only to start the construction but also for flood control mission.
|
Son La hydro power plants – The largest Hydro power projects in Vietnam applied the new technology – (Roller compacted concrete – RCC). RCC work is not only simple concrete pour, which required coordination to synchronize operation of extracting the materials, crushing and screening, batching plants - cold station, transport, electricity supply, water, etc ... just one stage is blocked off to stop the whole system.
|
Song Da - the name associated with hydroelectric projects and has become a familiar brand of the people of Vietnam. Not only in Sweden, a series of other works of Song Da is gradually asserted its position, brand name and strength, make up a leading group of Song Da construction field in Vietnam. To get success, it is contribution of a comprehensive leadership role and effectiveness of Party Group.
|
|
|